Huron Church Road Reconstruction


Girardot to College Northbound laneTecumseh to Giradot Southbound lane
Photos: Huron Church Road existing condition

Tecumseh Road West to College Avenue - Project Summary

  • Anticipated start date is April 6, 2021, with a 110-day timeline.
  • Work will take place 7 days per week and 24 hours per day as necessary to maintain schedule.
  • All businesses will be open during construction and access will be maintained at all times.

Stage 1:

  • Northbound traffic will be reduced to a single lane, routed on the east side of Huron Church Road, from Tecumseh Road to College Avenue
  • Southbound traffic will be reduced to two lanes, routed on the east side of Huron Church Road, from Tecumseh Road to College Avenue
  • No left turns will be allowed in the construction zone.
  • Access to businesses and Assumption College Catholic High School on the east side of Huron Church will be available, for northbound traffic only, during Stage 1.
  • Access to businesses on the west side of the road will not be open to local traffic.
  • Access to Millen Street and Girardot Street from Huron Church Road will not be available during Stage 1 of the work.
  • Pedestrian crossing shall be available at the signalized intersections of Tecumseh Road and College Avenue, in addition to the pedestrian bridge North of Girardot Street.

Stage 2:

  • Once Stage 1 is complete (plus/minus 55 days), traffic will be diverted onto the southbound lanes and the southbound lanes will be reconstructed.
  • Northbound traffic will be reduced to a single lane, routed on the west side of Huron Church Road, from Tecumseh Road to College Avenue.
  • Southbound traffic will be reduced to two lanes, routed on the west side of Huron Church Road, from Tecumseh Road to College Avenue.
  • During this phase, west side Huron Church business access will be available for southbound traffic only.
  • Access to Assumption College Catholic High School on the east side will still be only be available via California Avenue.
  • Pedestrian crossing shall be available at the signalized intersections of Tecumseh Road and College Avenue, in addition to the pedestrian bridge North of Girardot Street.

Traffic Control Drawings

Contracts Division
1531 Crawford Avenue
Windsor, Ontario
Canada
N8X 2A9